PMP認(rèn)證考試練習(xí)題及參考答案(五)
1. there are two major types of reserves used on projects. the _____ is for (usually major) scope changes that were not considered as part of
the original plan, whereas the _____ is to compensate for minor changes in estimating, escalation factors.
a. management reserve, unplanned allowance fund.
b. management reserve, contingency.
c. contingency fund, management reserve.
d. unplanned allowance fund, budgetary reserve.
e. unplanned reserve, planned reserve.
ans: c
2. to determine what causes the majority of quality problems in a process, a very useful tool is the:
a. cause and effect diagrams.
b. flow chart.
c. control chart.
d. pareto chart.
e. trend chart.來源:www.examda.com
ans: d
3. which of the following is not part of contract administration
a. contract award
b. performance control
c. financial control
d. contract closeout
e. all of the above are parts of contract administration.
ans: a
4. a(n) _____ system is designed to ensure the timely availability of nonhuman resources, and includes the cost in procurement, shipping/freight,
storage and loss.
a. inventory control.
b. materials management.
c. procurement.
d. all of the above.
e. a and c only.
ans: b

5. expectancy theory as applied to project management implies that:
a. the team will work the hardest on those goals that are clearly explained by the project manager
b. the more rewards that the project manager provides, the better the performance of the team
c. team members will work hardest for those project goals that also bring satisfaction to personal goals
d. employees will work hardest for those project goals which are accompanied by high levels of authority for the individual team members
e. none of the above
ans: c
6. non-verbal communication includes:
a. body movement
b. gestures來源:考試大網(wǎng)
c. facial expressions
d. the way we move our hands
e. all of the above
ans: e
7. the formal invitation to submit a price for specified goods/services is usually referred to as:
a. request for proposal
b. request for quotation
c. tender invitation
d. bid invitation
e. a and b only
ans: b
8. the project scope/charter baseline includes:
a. summary of background conditions defining the project.
b. organization, authority and responsibility relationships.
c. functions to be performed.
d. resource requirement schedule including time estimates.
e. all of the above.
ans: e
9. which of the following is not an input to quality planning?
a. scope statement.
b. regulations.
c. work results.
d. standards.
e. quality policy.
ans: c
10. which of the following networking methods allows us to show that the last 10% of one element cannot be completed until 62% of a previous
element has been completed?
a. pert
b. adm
c. pdm
d. all of the above.考試大(www.Examda。com)
e. a and c only.
ans: c
11. which of the following utility functions reflects risk-aversion:
a. uniform
b. increasing
c. decreasing
d. exponential
e. b and d only
ans: c
12. a deficiency in characteristics that render the quality of the material/service unacceptable is usually referred to as:
a. defective
b. defect
c. non-conformance來源:考試大網(wǎng)
d. poor workmanship
e. lack of fitness for use
ans: c
本文內(nèi)容來自自互聯(lián)網(wǎng)公開信息或用戶自發(fā)貢獻(xiàn),該文觀點僅代表作者本人,版權(quán)歸原作者所有。本站僅提供信息存儲空間服務(wù),不擁有所有權(quán),不承擔(dān)相關(guān)法律責(zé)任。若發(fā)現(xiàn)侵權(quán)或違規(guī)內(nèi)容請聯(lián)系電話4008352114或郵箱442699841@qq.com,核實后本網(wǎng)站將在24小時內(nèi)刪除侵權(quán)內(nèi)容。
本站推薦
- 1信息系統(tǒng)項目管理證書與PMP,為職業(yè)發(fā)展帶來的驚人機(jī)遇!
- 2信息系統(tǒng)項目管理師證書和pmp哪個更適合升職加薪?
- 3PMP項目管理泡軟件面臨的常見問題與挑戰(zhàn)分析
- 4PMP考試通過率及考生滿意度提升至90%以上:量化軟件項目管理成果的研究與實現(xiàn)
- 5歡迎登陸PMP項目管理系統(tǒng)——提升項目成功率的專業(yè)平臺!
- 6pmp證書和系統(tǒng)項目管理證書助你開啟高薪項目管理職場之路
- 7pmp證書助你馳騁職場與信息系統(tǒng)項目管理高薪秘籍曝光
- 8pmp證書助你開啟國際項目管理大門和信息系統(tǒng)項目管理師引領(lǐng)國內(nèi)項目管理之路
- 9PMP證書加持系統(tǒng)集成項目管理,開啟職場晉升新捷徑