PMP認(rèn)證考試練習(xí)題及參考答案(八)

申請免費(fèi)試用、咨詢電話:400-8352-114

1. overlapping activities on a project, such as design and construction, is referred to as:
a. fast tracking
b. risk conversion.
c. parallel management.
d. process improvement.
e. synchronous manufacturing來源:考試大網(wǎng)
ans: a

2. the major reason why a project manager would use written instead of oral communication is:
a. documentation
b. feedback
c. cost
d. barrier elimination
e. all of the above.
ans: a

3. the scope management provides:來源:考試大網(wǎng)
a. a basis for future decisions about the project.
b. a baseline to accomplish verification measures.
c. a baseline to evaluate potential scope changes.
d. all of the above.
e. b and c only.
ans: d

4. total project risk can be defined as:
a. the sum of the probabilities of project risks events times the sum of consequences of those risks
b. the sum of the products of each project risk event times its consequences
c. the sum of the consequences of all project risk events
d. the sum of the probabilities of all project risk events
e. 1 - the sum of the probabilities of all project risk events.
ans: b

5. which of the following statements about the cost of quality are true?
a. the cost of quality is the expense of nonconformance to requirements and specifications.
b. the cost of quality are mostly the direct responsibility of workers who are manufacturing the product.
c. quality control programs should be implemented when the cost of quality are deemed affordable by management.
d. a and b.來源:考
e. a and c
ans: a

6. a line manager who is asked to wear two hats and function as a project manager at the same time is likely to exercise:
a. authority
b. power
c. influence
d. all of the above]
e. a and b only
ans: d

7. including the customer in the process of project planning is:
a. slow and counterproductive.
b. essential in the definition and documentation of project goals.
c. necessary, but of limited value.
d. unnecessary because project goals are defined in the proposal stage.
e. none of the above.
ans: b

8. it is argumentative whether project managers actually control costs. which of the following is the most common element over which the
project manager may have some degree of control?
a. direct labor dollars
b. direct labor hours.www.Examda.CoM
c. overhead rates.
d. procurement costs.
e. none of the above.
ans: b

9. most quality problems:
a. originate in the quality department where the ultimate responsibility for quality rests.
b. originate on the shop floor because of waste and product rework.
c. are the results of management inattention to potential quality improvement ideas.
d. could be eliminated if shop supervisors monitored their work more closely.
e. a and b
ans: c

10. the "buy or make" decision is usually made during the:
a. acquisition cycle
b. contract evaluation cycle
c. requirements cycle
d. pre-award cycle
e. at any time that is convenient for the project manager
ans: c

11. the logical relationship that communicates a delay between the start/finish of one activity and the start/finish of another activity is referred to
as:
a. slackwww.Examda.CoM
b. free float.
c. restricted float.
d. level float.
e. lag
ans: e

12. which of the following actions is an example of risk response:
a. adjust project parameters (scope, time, quality ...)
b. reduce the probability of potential project risk events
c. reduce the consequences of potential project risk events
d. wait until a problem actually happens, then deal with it in the most effective and efficient manner.
e. a, b and c only
ans: e

網(wǎng)站提醒和聲明

本文內(nèi)容來自自互聯(lián)網(wǎng)公開信息或用戶自發(fā)貢獻(xiàn),該文觀點(diǎn)僅代表作者本人,版權(quán)歸原作者所有。本站僅提供信息存儲空間服務(wù),不擁有所有權(quán),不承擔(dān)相關(guān)法律責(zé)任。若發(fā)現(xiàn)侵權(quán)或違規(guī)內(nèi)容請聯(lián)系電話4008352114或郵箱442699841@qq.com,核實(shí)后本網(wǎng)站將在24小時內(nèi)刪除侵權(quán)內(nèi)容。

發(fā)布:2026-02-28 10:29    編輯:xiaona    [打印此頁]    [關(guān)閉]

泛普軟件項(xiàng)目管理工具其他應(yīng)用

項(xiàng)目管理工具 禪道項(xiàng)目管理軟件 夢龍項(xiàng)目管理軟件 微軟項(xiàng)目管理軟件 裝飾管理系統(tǒng) 裝修預(yù)算軟件 項(xiàng)目計(jì)劃軟件 項(xiàng)目進(jìn)度管理軟件 軟件項(xiàng)目管理工具 材料管理軟件 工程項(xiàng)目管理軟件系統(tǒng) 項(xiàng)目管理系統(tǒng) 施工管理軟件 建筑工程項(xiàng)目管理軟件 工程管理軟件