1. which of the following is associated with a buyer's request for material to meet a particular need:
a. material warranty
b. material guarantees
c. implied warranty of salability
d. implied warranty of fitness for a particular purpose
e. a and c onlywww.Examda.CoM
ans: d
2. a project manager trying to communicate accurately to the team should use:
a. the language of the team members
b. the language of the project manager
c. non-verbal methods
d. written memos
e. all of the above.
ans: a
3. an advertiser who uses a movie or sports star to endorse a product is trying to use power.
a. expert
b. legitimate
c. reward
d. influential
e. referent
ans: e來(lái)源:考試大
4. control chart theory is based on the differentiation of the causes of variations in quality. variations may be produced by assignable causes.
all of the following are examples of assignable causes except:
a. differences among machines.
b. differences among workers.
c. differences among materials.
d. differences in each of these factors over time.
e. none of the above (all are examples)
ans: e

5. giving a part of project work to a contractor is an example of:
a. risk mitigation
b. risk assignment
c. risk delegation
d. risk deflection
e. risk assumption來(lái)源:www.examda.com
ans: d
6. proper implementation of project management will guarantee that:
a. budgets will be met.
b. schedules will be adhered to.
c. quality/performance will be met.
d. the project will be a success.
e. none of the above.
ans: e
7. the most effective means of determining the cost of a project is to price out the _____.
a. work breakdown structure.
b. linear responsibility chart.
c. project charter.
d. scope statement.
e. management plan.
ans: a
8. which method shown below is acceptable for reducing cost or shortening the schedule?
a. "crashing"
b. changing scope.
c. performing activities in parallel rather than in series.
d. all of the above.
e. a and c only.考試大(www.Examda。com)
ans: d
9. which of the following terms is used to describe the receipt issued by a carrier for items to be delivered to a third party:
a. free on board
b. receipt for merchandise
c. packaging list
d. loading list
e. bill of lading
ans: e
10. a computer tape which contains historical project information is called ____ tape.
a. database
b. baseline.
c. archive.
d. lessons learned.
e. life cycle summary.
ans: c
11. according to herzberg, which of the following is a motivational factor?
a. pay
b. hygiene needs
c. achievementwww.Examda.CoM
d. working conditions
e. vacation time
ans: c
12. communication in both project and non-project-driven organizations should occur in directions.
a. one
b. two
c. three
d. four
e. five
ans: e
本文內(nèi)容來(lái)自自互聯(lián)網(wǎng)公開信息或用戶自發(fā)貢獻(xiàn),該文觀點(diǎn)僅代表作者本人,版權(quán)歸原作者所有。本站僅提供信息存儲(chǔ)空間服務(wù),不擁有所有權(quán),不承擔(dān)相關(guān)法律責(zé)任。若發(fā)現(xiàn)侵權(quán)或違規(guī)內(nèi)容請(qǐng)聯(lián)系電話4008352114或郵箱442699841@qq.com,核實(shí)后本網(wǎng)站將在24小時(shí)內(nèi)刪除侵權(quán)內(nèi)容。
本站推薦
- 1信息系統(tǒng)項(xiàng)目管理證書與PMP,為職業(yè)發(fā)展帶來(lái)的驚人機(jī)遇!
- 2信息系統(tǒng)項(xiàng)目管理師證書和pmp哪個(gè)更適合升職加薪?
- 3PMP項(xiàng)目管理泡軟件面臨的常見(jiàn)問(wèn)題與挑戰(zhàn)分析
- 4PMP考試通過(guò)率及考生滿意度提升至90%以上:量化軟件項(xiàng)目管理成果的研究與實(shí)現(xiàn)
- 5歡迎登陸PMP項(xiàng)目管理系統(tǒng)——提升項(xiàng)目成功率的專業(yè)平臺(tái)!
- 6pmp證書和系統(tǒng)項(xiàng)目管理證書助你開啟高薪項(xiàng)目管理職場(chǎng)之路
- 7pmp證書助你馳騁職場(chǎng)與信息系統(tǒng)項(xiàng)目管理高薪秘籍曝光
- 8pmp證書助你開啟國(guó)際項(xiàng)目管理大門和信息系統(tǒng)項(xiàng)目管理師引領(lǐng)國(guó)內(nèi)項(xiàng)目管理之路
- 9PMP證書加持系統(tǒng)集成項(xiàng)目管理,開啟職場(chǎng)晉升新捷徑