1 The budgeted cost of the work performed (BCWP) for a task that has just been completed can be calculated by:A Multiplying the actual hours worked on the project by the budgeted labor rate.
B Multiplying the budgeted hours to complete the task by the budgeted labor rate.
C Dividing the actual hours required to complete the task by the budgeted labor rate.
D Cannot be determined.
E None of the above 來源:考試大網(wǎng)
ans:B
2 The methods and techniques for determining the economic costs, the environmental impact, the economic returns, and the probability for success are called:
A Feasibility studies.
B Bills of materials.
C Pert charts.
D Managerial reserves.
E None of the above
ans:A
3 The planned cost for the total project at its inception is called the _____.
A Cost of goods sold.
B Depreciable value.
C Budgeted cost.
D All of the above.
E B and C only. 來源:www.examda.com
ans:C
4 Which of the following is not a measure of the profitability of a project or program?
A Return on original investment.
B Net present value.
C Depreciation.
D Discounted cash flow.
E None of the above
ans:C
5 The budget associated with scope changes that have been approved but not planned for yet, is referred to a(n) _____ budget.
A Unauditable.
B Undistributed.
C Preauthorized.
D Contingency.
E In-process.
ans:B
6 Using the situation stated in the Special window, what is the total fixed costs for manufacturing the widgets?
A ¥3,000
B ¥27,000 來源:考試大
C ¥27,270
D ¥1,335
E ¥1,000
ans:E
7 Using the situation stated in the Special window, the labor rate cost variance is:
A ¥66,927
B ¥68,329
C ¥386
D ¥-0
E ¥18.36
ans:D
8 In project-driven companies, costs are usually billed againest the project based upon:
A The burdened labor rate of the actual employees who performed the work.
B The burdened labor rate of the line organization average salary.
C The burdened labor rate of the company average salary.
D The burdened labor rate of the average salary of the project team members.
E None of the above.
ans:A
9 The most common method for pricing out non-burdened labor hours for a three year project would be to:
A Price out the hours at the actual salary of the people to be assigned.
B Price out the work using a company-wide average labor rate.
C Price out the work using a functional group average labor rate.
D All of the above.
E A and B only. 來源:www.examda.com
ans:C
10 An element in the WBS was estimated to require 1 month for completion with 1000 hours of labor and a burdened cost of $50K. The task was completed in 1000 hours but a burdened cost of $60K. The most likely reason for the increase would be:
A Higher salaried employees were assigned.
B Overtime was required.
C The overhead rate increased.
D Employee salaries had increased.
E Any of the above
ans:E
11 During a project review meeting, you discover that your $250,000 project has a negative schedule variance of $20,000 which equates to 12% of the work scheduled to this point of time. You can therefore conclude that:
A The project will be completed late.
B The critical path has been lengthened.
C the costs are being overrun.
D Overtime will be required to maintain the original critical path.
E None of the above.
ans:E
12 Using the situation stated in the Special window, the total price variance of direct material is:
A ¥80,245
B ¥-4,236 來源:考試大網(wǎng)
C ¥-3,479
D ¥1
E ¥83,994.00
ans:C
本文內(nèi)容來自自互聯(lián)網(wǎng)公開信息或用戶自發(fā)貢獻(xiàn),該文觀點(diǎn)僅代表作者本人,版權(quán)歸原作者所有。本站僅提供信息存儲(chǔ)空間服務(wù),不擁有所有權(quán),不承擔(dān)相關(guān)法律責(zé)任。若發(fā)現(xiàn)侵權(quán)或違規(guī)內(nèi)容請(qǐng)聯(lián)系電話4008352114或郵箱442699841@qq.com,核實(shí)后本網(wǎng)站將在24小時(shí)內(nèi)刪除侵權(quán)內(nèi)容。
本站推薦
- 1信息系統(tǒng)項(xiàng)目管理證書與PMP,為職業(yè)發(fā)展帶來的驚人機(jī)遇!
- 2信息系統(tǒng)項(xiàng)目管理師證書和pmp哪個(gè)更適合升職加薪?
- 3PMP項(xiàng)目管理泡軟件面臨的常見問題與挑戰(zhàn)分析
- 4PMP考試通過率及考生滿意度提升至90%以上:量化軟件項(xiàng)目管理成果的研究與實(shí)現(xiàn)
- 5歡迎登陸PMP項(xiàng)目管理系統(tǒng)——提升項(xiàng)目成功率的專業(yè)平臺(tái)!
- 6pmp證書和系統(tǒng)項(xiàng)目管理證書助你開啟高薪項(xiàng)目管理職場(chǎng)之路
- 7pmp證書助你馳騁職場(chǎng)與信息系統(tǒng)項(xiàng)目管理高薪秘籍曝光
- 8pmp證書助你開啟國(guó)際項(xiàng)目管理大門和信息系統(tǒng)項(xiàng)目管理師引領(lǐng)國(guó)內(nèi)項(xiàng)目管理之路
- 9PMP證書加持系統(tǒng)集成項(xiàng)目管理,開啟職場(chǎng)晉升新捷徑