PMP認證考試練習題及參考答案(三十八)
A 10-12%
B 2-3 %
C 6-8%
D 3-5%
E more than 15 %
ans:D
2 _____ of the extra costs of the project can often be attributed to a lack of quality.
A 12%
B 15%
C 20%
D 25%
E less than 10% 來源:考試大
ans:C
3 CIP embodies which of the following principals?
A constancy of purpose
B customer focus and involvement
C total involvement
D teamwork
E All of the above.
ans:E
4 The key ingredient to a successful quality management program are _____.
A management's quality philosophy, operational quality assurance and operational quality control.
B quality evaluation methods and functional quality integrators.
C technical quality administration, the technical quality specifications, and the quality process review.
D quality evaluation methods, quality progress reviews and the technical quality specifications.
E All of the above.
ans:A
5 At least _____of the cost of quality are the direct responsibility of management.
A 25%
B 85%
C 50%
D 100%
E 33%
ans:B
6 Non-conformance penalties are a form of _____.
A quality incentive
B risk sharing
C contract negotiations
D quality assurance programs
E None of the above. www.Examda.CoM
ans:C
7 Quality Improvement Programs are normally associated with which two of the following?
A Juran and Crosby
B Juran and Deming
C Crosby and Deming
D Deming and the Japanese
E Crosby and the Japanese
ans:D
8 The initial cost of a product and the product's operation and maintenance costs _____ .
A increases perceived value when balanced.
B are incidental to each other because initial costs are "sunk"
C decreases design costs as operation periods increase
D provides perceived function value and product social dysfunction
E are integrally related with each other because initial costs are "sunk".
ans:A
9 Quality control is normally performed by the _____ .
A QA personnel
B project team
C operating personnel
D project management
E None of the above.
ans:C
10 Quality and _____ are directly related.
A productivity
B cost overruns
C scope control 考試大(www.Examda。com)
D Pareto diagram
E None of the above.
ans:A
11 _____ best describes the goal of a project in its relationship with the customer, from initial contact through delivery.
A fitness for use
B customer satisfaction
C conformance to requirements
D fitness for purpose
E All of the above.
ans:B
12 The primary consideration of product management is to know the _____.
A probability of product's performance with specified parameters
B ability the product has to perform its intended function
C ability of a product to be produced within existing parameters
D functionality the product will provide over its useful life
E All of the above
ans:D
本文內(nèi)容來自自互聯(lián)網(wǎng)公開信息或用戶自發(fā)貢獻,該文觀點僅代表作者本人,版權(quán)歸原作者所有。本站僅提供信息存儲空間服務,不擁有所有權(quán),不承擔相關(guān)法律責任。若發(fā)現(xiàn)侵權(quán)或違規(guī)內(nèi)容請聯(lián)系電話4008352114或郵箱442699841@qq.com,核實后本網(wǎng)站將在24小時內(nèi)刪除侵權(quán)內(nèi)容。
本站推薦
- 1信息系統(tǒng)項目管理證書與PMP,為職業(yè)發(fā)展帶來的驚人機遇!
- 2信息系統(tǒng)項目管理師證書和pmp哪個更適合升職加薪?
- 3PMP項目管理泡軟件面臨的常見問題與挑戰(zhàn)分析
- 4PMP考試通過率及考生滿意度提升至90%以上:量化軟件項目管理成果的研究與實現(xiàn)
- 5歡迎登陸PMP項目管理系統(tǒng)——提升項目成功率的專業(yè)平臺!
- 6pmp證書和系統(tǒng)項目管理證書助你開啟高薪項目管理職場之路
- 7pmp證書助你馳騁職場與信息系統(tǒng)項目管理高薪秘籍曝光
- 8pmp證書助你開啟國際項目管理大門和信息系統(tǒng)項目管理師引領(lǐng)國內(nèi)項目管理之路
- 9PMP證書加持系統(tǒng)集成項目管理,開啟職場晉升新捷徑