PMP認(rèn)證考試練習(xí)題及參考答案(四十)
A the use of quality circles.
B small, continuous improvements in quality control.
C the use of worker suggestion systems.
D the use of quality control charts. 來源:www.examda.com
E focusing quality control efforts on production outputs.
ans:E
2 Control chart theory is based on the differentiation of the causes of variations in quality. Variations may be produced by assignable causes. All of the following are examples of assignable causes except:
A differences among machines.
B differences among workers.
C differences among materials.
D differences in each of these factors over time.
E None of the above (all are examples)
ans:E
3 The rule of seven used by quality control engineers states that if a run of seven or more samples lays on one side of the process mean, then the process is out of control. What is the probability that this condition is the result of random variations.
A 14.30%
B 3.12%
C 2.73% www.Examda.CoM
D 1.56%
E 0.78%
ans:D
4 Two sources of variation in the length of hex bolts exist. Production variation and measurement error. The QC manager knows that the standard deviation from these sources is 0.24" and 0.43" , respectively. What is the total standard deviation.
A .10 inch.
B .19 inch.
C .34 inch.
D .49 inch.
E .67 inch.
ans:D
5 Affinity diagrams are used to:
A determine if a process is in control.
B determine root cause.
C show the relationship among variables.
D categorize large amounts of data.
E None of the above.
ans:D
6 Which quality management tool would be used to determine potential causes of a production problem?
A control chart.
B Ishikawa diagram.
C scatter diagram.
D histogram. 來源:www.examda.com
E run chart.
ans:B
7 Which of the following is not an input to quality planning?
A scope statement.
B regulations.
C work results.
D standards.
E quality policy.
ans:C
8 To determine what causes the majority of quality problems in a process, a very useful tool is the:
A cause and effect diagrams.
B flow chart.
C control chart.
D pareto chart.
E trend chart.
ans:D
9 For a given characteristic in a construction process, the standard deviation associated with production variation is 0.8", and the standard deviation associated with measurement variation is 0.6". The total standard deviation for this characteristic is:
A 1.4"
B 1.2".
C 1.0"
D 0.8"
E 0.2"
ans:C
10 Assignable cause or special variation is:
A is indicated when a point falls outside the control limits.
B is indicated when a point falls outside the specification limits.
C is indicated when a run of seven or more points fall above the center line of a standard control chart.
D is indicated when a run of seven or more points fall below the center line of a standard control chart.
E A, C, and D.
ans:E www.Examda.CoM
11 Quality control charts show a characteristic of the product or service against:
A the specification limits.
B customer requirements.
C control limits based on three standard deviations in each direction.
D control limits based on six standard deviations in each direction.
E A and D only
ans:C
12 Which of the following constitute Juran's "quality trilogy":
A planning, inspection, control.
B planning, improvement, control.
C planning, organization, control.
D product, price, customer.
E design, build, deliver.
ans:B
本文內(nèi)容來自自互聯(lián)網(wǎng)公開信息或用戶自發(fā)貢獻(xiàn),該文觀點(diǎn)僅代表作者本人,版權(quán)歸原作者所有。本站僅提供信息存儲空間服務(wù),不擁有所有權(quán),不承擔(dān)相關(guān)法律責(zé)任。若發(fā)現(xiàn)侵權(quán)或違規(guī)內(nèi)容請聯(lián)系電話4008352114或郵箱442699841@qq.com,核實(shí)后本網(wǎng)站將在24小時內(nèi)刪除侵權(quán)內(nèi)容。
本站推薦
- 1信息系統(tǒng)項目管理證書與PMP,為職業(yè)發(fā)展帶來的驚人機(jī)遇!
- 2信息系統(tǒng)項目管理師證書和pmp哪個更適合升職加薪?
- 3PMP項目管理泡軟件面臨的常見問題與挑戰(zhàn)分析
- 4PMP考試通過率及考生滿意度提升至90%以上:量化軟件項目管理成果的研究與實(shí)現(xiàn)
- 5歡迎登陸PMP項目管理系統(tǒng)——提升項目成功率的專業(yè)平臺!
- 6pmp證書和系統(tǒng)項目管理證書助你開啟高薪項目管理職場之路
- 7pmp證書助你馳騁職場與信息系統(tǒng)項目管理高薪秘籍曝光
- 8pmp證書助你開啟國際項目管理大門和信息系統(tǒng)項目管理師引領(lǐng)國內(nèi)項目管理之路
- 9PMP證書加持系統(tǒng)集成項目管理,開啟職場晉升新捷徑