PMP認證考試練習題及參考答案(五十五)
A Demand forecast
B Price forecast
C Supply forecast
D Production forecast
E None of the above.
ans:B
2 Fixed-price and incentive-type contracts place responsibility for performance and financial risks associated with delay or non-performance on the:
A Buyer
B Third party
C Contractor
D All of the above
E None of the above
ans:C
3 The _____ specification delineates specific measurable capabilities or parameters for which a product can be tested as part of the acceptance procedure.
A Performance
B Functional
C Technical 考試大-全國最大教育類網(wǎng)站(www.Examda。com)
D Base Line
E None of the above.
ans:A
4 There are four methods of government procurement. Which is not one of these methods?
A Assistance
B Sealed bidding
C Competitive proposals
D Acquisition
E Small purchases
ans:D
5 Which is not a consideration in a make or buy decision?
A Cost factors (least cost alternatives)
B Competitors' method of sourcing
C Existence of sufficient administration/technical personnel
D Political and social factors
E None of the above.
ans:B
6 By which means is a contractor able to control cost overruns due to changing requirements?
A Project data review
B Change order
C Purchase order amendment
D Change control
E None of the above.
ans:D
7 _____ is a formal invitation containing a scope of work which seeks a formal response (proposal) describing both methodology and compensation to form the basis of a contract.
A Request for proposal
B Invitation to bid
C Request for quotation
D Intention for bid
E None of the above.
ans:A
8 _____ is a method of procurement where a contract results from a bid which may be changed through bargaining.
A Acquisition
B Contract negotiation
C Procurement
D Purchase negotiation
E None of the above.
ans:B
9 _____ is a narrative description of the work to be accomplished or resource to be supplied.
A Purchase order
B Level of effort work
C Scope of work
D Contract stipulation 考試大-全國最大教育類網(wǎng)站(www.Examda。com)
E None of the above.
ans:C
10 The cost of corrective action taken by the purchaser and chargeable to the supplier under the terms of the contract is:
A Payment authorization
B Bid cost considerations
C Release payment
D Back charge
E None of the above.
ans:D
11 Cost Reimbursable contracts are equivalent to:
A Cost plus contracts
B Fixed plus contracts
C Progress payment contracts
D Back charge contracts
E None of the above.
ans:A
12 Which is not part of the purchasing cycle?
A Defined need
B Transmit need
C Inspection
D Prepare and issue purchase order
E A and D
ans:C
本文內(nèi)容來自自互聯(lián)網(wǎng)公開信息或用戶自發(fā)貢獻,該文觀點僅代表作者本人,版權(quán)歸原作者所有。本站僅提供信息存儲空間服務,不擁有所有權(quán),不承擔相關(guān)法律責任。若發(fā)現(xiàn)侵權(quán)或違規(guī)內(nèi)容請聯(lián)系電話4008352114或郵箱442699841@qq.com,核實后本網(wǎng)站將在24小時內(nèi)刪除侵權(quán)內(nèi)容。
本站推薦
- 1信息系統(tǒng)項目管理證書與PMP,為職業(yè)發(fā)展帶來的驚人機遇!
- 2信息系統(tǒng)項目管理師證書和pmp哪個更適合升職加薪?
- 3PMP項目管理泡軟件面臨的常見問題與挑戰(zhàn)分析
- 4PMP考試通過率及考生滿意度提升至90%以上:量化軟件項目管理成果的研究與實現(xiàn)
- 5歡迎登陸PMP項目管理系統(tǒng)——提升項目成功率的專業(yè)平臺!
- 6pmp證書和系統(tǒng)項目管理證書助你開啟高薪項目管理職場之路
- 7pmp證書助你馳騁職場與信息系統(tǒng)項目管理高薪秘籍曝光
- 8pmp證書助你開啟國際項目管理大門和信息系統(tǒng)項目管理師引領(lǐng)國內(nèi)項目管理之路
- 9PMP證書加持系統(tǒng)集成項目管理,開啟職場晉升新捷徑