PMP美國項目管理認(rèn)證的模擬考試的樣題8
A. Analysis of alternatives.
B. Revisions/replanning.
C. Resource allocation.
D. Modification or updating of goals and objectives.
E. All of the above.
ANS: E
2. The basic terminology for networks includes:
A. Activities, events, manpower, skill levels and slack.
B. Activities, documentation, events, manpower and skill
levels.
C. Slack, activities, events, and time estimates.
D. Time estimates, slack, sponsorship involvement, and
activities.
E. Time estimates, slack time, report writing, life
cycle phases, and crashing times.
ANS: C
3. The project manager must receive reports and
briefings from engineers, contracting officers,
procurement personnel and marketing people.
The project manager’s communication dilemma is one of:
A. encoding
B. decoding
C. choice of a medium
D. one-way communication
E. All of the above.
ANS: E
4. The technique most commonly used to determine the
profitability of a project includes _____ methods.
A. Net present value (NPV).
B. Return on investment (ROI).
C. Discounted cash flow (DCF)
D. Payout time and risk sensitivity analysis.
E. All of the above.
ANS: E
5. Which of the following are part of the purchasing
cycle:
A. define need
B. prepare and issue purchase order
C. inspect incoming goods
D. All of the above.
E. A and B only
ANS: E
6. Which of the following is closest to Juran’s
definition of Quality:
A. conformance to requirements.
B. fitness for use.
C. continuous improvement.
D. customer focus.
E. All of the above.
ANS: B
7. A project element which lies between two events is
called:
A. An activity.
B. A critical path method.
C. A slack milestone.
D. A timing slot.
E. A calendar completion point.
ANS: A
8. Employee unions would most likely satisfy which
level in Maslow’s hierarchy of needs?
A. Belonging
B. Self-actualization
C. Esteem
D. Safety
E. Empowerment
ANS: A
9. Management calls a meeting to explain to all
employees the new benefits package for the rank and
file. This is an example of:
A. Upward communication
B. Downward communication
C. One-way communication
D. Two-way communication
E. None of the above.
ANS: C
10. Project management/project planning is most closely
aligned with:
A. Long range/strategic planning (5 years or more).
B. Intermediate range planning (1 to 5 years)
C. Short range/tactical planning (1 year or less).
D. All of the above.
E. B and C.
ANS: E
本文內(nèi)容來自自互聯(lián)網(wǎng)公開信息或用戶自發(fā)貢獻(xiàn),該文觀點僅代表作者本人,版權(quán)歸原作者所有。本站僅提供信息存儲空間服務(wù),不擁有所有權(quán),不承擔(dān)相關(guān)法律責(zé)任。若發(fā)現(xiàn)侵權(quán)或違規(guī)內(nèi)容請聯(lián)系電話4008352114或郵箱442699841@qq.com,核實后本網(wǎng)站將在24小時內(nèi)刪除侵權(quán)內(nèi)容。
本站推薦
- 1信息系統(tǒng)項目管理證書與PMP,為職業(yè)發(fā)展帶來的驚人機(jī)遇!
- 2信息系統(tǒng)項目管理師證書和pmp哪個更適合升職加薪?
- 3PMP項目管理泡軟件面臨的常見問題與挑戰(zhàn)分析
- 4PMP考試通過率及考生滿意度提升至90%以上:量化軟件項目管理成果的研究與實現(xiàn)
- 5歡迎登陸PMP項目管理系統(tǒng)——提升項目成功率的專業(yè)平臺!
- 6pmp證書和系統(tǒng)項目管理證書助你開啟高薪項目管理職場之路
- 7pmp證書助你馳騁職場與信息系統(tǒng)項目管理高薪秘籍曝光
- 8pmp證書助你開啟國際項目管理大門和信息系統(tǒng)項目管理師引領(lǐng)國內(nèi)項目管理之路
- 9PMP證書加持系統(tǒng)集成項目管理,開啟職場晉升新捷徑