項目管理:PMP模擬題精選4
As applied to projects, temporary means that--
a. Projects are short in duration
b. Every project has a definite beginning and end
c. The undertaking will end at an undetermined time in the future
d. Projects can be canceled at any time
Qustions 3:
Which of the following is an example a constraint in project plan development--
a. Records fo past performance
b. Financial reports from similar projects
c. A predefined budget
d. Lessons learned from prior projects
Qustions 5:
The management-by-objectives technique addresses all the following except--
a. Establishing unambiguous and realistic objectives
b. Periodically evaluating whether project objectives have been achieved
c. Promoting participation, team building, and commitment to the project
d. Establishing a specific career path for a project team member
Qustions 2:
All the following are examples of tools and techniques used in integration management except--
a. The work authorization system
b. Organizational procedures
c. Product skills and knowledge
d. Organizational policies
Qustions 4:
Performance measurement techniques are useful in overall change control because they --
a. Help show the status of the project
b. Measure overall project progress
c. Summarize information on the project for reporting to stakeholders
d. Help assess whether variances from the plan require corrective action
Qustions 6:
A work authorization system is a --
a. Work breakdown structure showing individual work elements
b. Formal procedure for sanctioning work so that it is done at the right time in the proper sequence
c. Method to ensure that each person on the project team knows the work elements that are his or her responsibility
d. System to help measure performance in terms of work completed versus work planned
本文內(nèi)容來自自互聯(lián)網(wǎng)公開信息或用戶自發(fā)貢獻,該文觀點僅代表作者本人,版權(quán)歸原作者所有。本站僅提供信息存儲空間服務,不擁有所有權(quán),不承擔相關(guān)法律責任。若發(fā)現(xiàn)侵權(quán)或違規(guī)內(nèi)容請聯(lián)系電話4008352114或郵箱442699841@qq.com,核實后本網(wǎng)站將在24小時內(nèi)刪除侵權(quán)內(nèi)容。
本站推薦
- 1企業(yè)級管理中臺+工程項目管理級中臺,實現(xiàn)業(yè)務和資金、費用、成本管理的一體化的平臺
- 2工程公司的管理系統(tǒng)不僅限于項目管理,公司級的管理才是企業(yè)基業(yè)長青的基石
- 3工程項目管理系統(tǒng)的實施與企業(yè)主要功能優(yōu)化調(diào)整
- 4泛普工程項目管理系統(tǒng):工程企業(yè)精細化管理的利器
- 5基建項目管理系統(tǒng)的調(diào)試、檔案與考勤管理詳解
- 6甲方投資項目管理系統(tǒng)的全周期管控與技術(shù)架構(gòu)解析
- 7基建項目管理平臺的構(gòu)建總包管控與全周期管理新體系
- 8基建項目管理平臺的合約規(guī)劃與設計協(xié)作詳細介紹
- 9基建項目管理的新技術(shù)應用及設計變更操作介紹