1. which of the following is referred to as payback period:
a. the number of periods required to recover the initial investment
b. the rate of return on the investment
c. the number of periods required to bring project cost back to the original budget, based on current performance
d. loan payment schedule
e. none of the above
ans: a
2. which one of the following is not an acquisition method?
a. advertising
b. invitation
c. negotiation
d. purchase考試大論壇
e. all are acquisition methods
ans: a
3. at least _____of the cost of quality are the direct responsibility of management.
a. 0.25
b. 0.85
c. 0.5
d. 1
e. 0.33
ans: b
4. fast tracking means to:
a. speed up a project through parallel tasks.
b. swap one task for another.
c. reduce the number of tasks if possible.
d. b and c.
e. none of the above.
ans: a來源:考試大網(wǎng)

5. formal written correspondence is mandated in which of the following situations:
a. product undergoes casual in-house testing
b. client requests additional work not covered under contract
c. project manager calls a meeting
d. b and c only
e. none of the above
ans: b
6. the delphi method is _____ .
a. used to derive a consensus arriving at a convergent solution
b. useful in determining probability relating to future events.
c. used with questionnaires based on established scenarios.
d. continued as an iterative process until a solution is reached.
e. all of the above.
ans: e
7. the positive value of conflict is underestimated. properly managed, conflict is a valuable tool, particularly when
a. a diversion is needed
b. conflictive situations are in their early stages and emotional involvement is low
c. conflictive situations are in their late stages and emotional involvement is high
d. conflict may cause a loss of status or position power
e.
ans: b
8. under the terms of 2/10 net 30, the buyer may:來源:考試大
a. deduct 10% of the invoice amount for payment within 30 days
b. deduct 2% of the invoice for payment within 10 days
c. incurs a penalty on 10% for payments more than 30 days late
d. settle the invoice with 2 equal payments; one within 10 days and the other within 30 days
e. none of the above
ans: b
9. which of the following can result in misinterpretation of the statement of work?
a. using imprecise language (i.e. nearly, approximately)
b. mixing tasks, specifications, special instructions and approvals
c. no pattern, structure or chronological order
d. wide variation in the size of tasks or details of work
e. all of the above
ans: e
10. amount at stake is the _____ .
a. function of planned time/real time project costs.
b. risk identified in successful project completions.
c. (standard project deviation + expected costs)/6
d. cost of investment loss + least cost to restore status quo.
e. inherent risk at conception altered by standard project deviations.來源:考試大網(wǎng)
ans: d
11. in communications management, to assimilate through the mind or senses (as in new ideas) is the process of
a. understanding
b. communicating
c. receiving
d. decoding
e. comprehending
ans: c
12. in general, the best long-lasting approach to settling project conflict is the _____ approach .
a. problem solving
b. compromise
c. withdrawal
d. smoothing
e. forcing
ans: a
本文內(nèi)容來自自互聯(lián)網(wǎng)公開信息或用戶自發(fā)貢獻,該文觀點僅代表作者本人,版權(quán)歸原作者所有。本站僅提供信息存儲空間服務(wù),不擁有所有權(quán),不承擔(dān)相關(guān)法律責(zé)任。若發(fā)現(xiàn)侵權(quán)或違規(guī)內(nèi)容請聯(lián)系電話4008352114或郵箱442699841@qq.com,核實后本網(wǎng)站將在24小時內(nèi)刪除侵權(quán)內(nèi)容。
本站推薦
- 1信息系統(tǒng)項目管理證書與PMP,為職業(yè)發(fā)展帶來的驚人機遇!
- 2信息系統(tǒng)項目管理師證書和pmp哪個更適合升職加薪?
- 3PMP項目管理泡軟件面臨的常見問題與挑戰(zhàn)分析
- 4PMP考試通過率及考生滿意度提升至90%以上:量化軟件項目管理成果的研究與實現(xiàn)
- 5歡迎登陸PMP項目管理系統(tǒng)——提升項目成功率的專業(yè)平臺!
- 6pmp證書和系統(tǒng)項目管理證書助你開啟高薪項目管理職場之路
- 7pmp證書助你馳騁職場與信息系統(tǒng)項目管理高薪秘籍曝光
- 8pmp證書助你開啟國際項目管理大門和信息系統(tǒng)項目管理師引領(lǐng)國內(nèi)項目管理之路
- 9PMP證書加持系統(tǒng)集成項目管理,開啟職場晉升新捷徑