PMP認證考試練習(xí)題及參考答案(二十八)
1 A task-oriented family tree of activities is a:
A Detailed plan.
B Linear responsibility chart.
C Work breakdown structure.
D Cost account coding system.
E Work package description.
ans:C
2 Management plans include all of the following except:
A Organization of project.
B Job descriptions.
C Policies and procedures.
D Linear responsibility charts. http://ks.examda.com
E Scope baseline.
ans:E
3 A comprehensive definition of scope management would be:
A Managing a project in terms of its objective through the concept, development, implementation, and termination phases of a project.
B Approval of the scope baseline.
C Approval of the detailed project charter.
D Configuration control.
E Approved detailed planning including budgets, resource allocation, linear responsibility charts and management sponsorship.
ans:A
4 The process of choosing/documenting the best approach to achieve the project objectives is part of:
A The scope baseline.
B Scope authorization
C Scope definition 來源:考試大
D Scope planning.
E All of the above.
ans:D
5 A completion of a local government study resides on your critical path. This would most likely be referred to as:
A Soft logic
B Hard logic
C An external dependency
D A mandatory dependency
E A lost cause
ans:C
6 Which of the following can affect network durations?
A Skills of the resource pool
B Calendar dates
C Constraints
D All of the above
E A and B only
ans:E
7 Sources for data on activity durations and resource requirements can be gathered from which of the following:
A Past project records (historical data)
B Commercial techniques (standard practices, rules of thumb)
C Past project team members knowledge (experience, oldtimers)
D All of the above www.Examda.CoM
E A and C only
ans:D
8 The erection of foundation formwork before the placement of foundation concrete would be an example of a _____ dependency.
A Discretionary
B Mandatory
C External
D Soft logic
E Subcontracted
ans:B
9 "Hard logic" in the preparation of a network refers to:
A Discretionay dependencies
B External depenencies
C Mandatory dependencies
D All of the above
E A abd B only
ans:C
10 The difference between a project and a program is that:
A A program is made up of multiple projects
B A program requires at least three times longer to plan than a project
C A project is a one-shot deal while a program is on-going
D A and C
E B and C
ans:D
11 As a control tool, the bar chart (Gantt) methods is most beneficial for:
A rearranging conflicting tasks
B depicting actual versus planned tasks
C showing the outer dependencies of tasks
D A and C.
E A and D
ans:B
12 You are managing an internal project where a vice president from the user group is acting as the sponsor. You have just been informed by your team that the critical path has slipped by three weeks. You should:
A Immediately inform the sponsor and ask for advice
B Do nothing until the slippage occurs
C See the sponsor after you have evaluated alternatives, recommendations, and performed an impact analysis
D Look for someone to blame before you see the sponsor
E Inform your senior management of the problem and tell them that you will get back to them after you assessed the situation
ans:C
本文內(nèi)容來自自互聯(lián)網(wǎng)公開信息或用戶自發(fā)貢獻,該文觀點僅代表作者本人,版權(quán)歸原作者所有。本站僅提供信息存儲空間服務(wù),不擁有所有權(quán),不承擔(dān)相關(guān)法律責(zé)任。若發(fā)現(xiàn)侵權(quán)或違規(guī)內(nèi)容請聯(lián)系電話4008352114或郵箱442699841@qq.com,核實后本網(wǎng)站將在24小時內(nèi)刪除侵權(quán)內(nèi)容。
本站推薦
- 1信息系統(tǒng)項目管理證書與PMP,為職業(yè)發(fā)展帶來的驚人機遇!
- 2信息系統(tǒng)項目管理師證書和pmp哪個更適合升職加薪?
- 3PMP項目管理泡軟件面臨的常見問題與挑戰(zhàn)分析
- 4PMP考試通過率及考生滿意度提升至90%以上:量化軟件項目管理成果的研究與實現(xiàn)
- 5歡迎登陸PMP項目管理系統(tǒng)——提升項目成功率的專業(yè)平臺!
- 6pmp證書和系統(tǒng)項目管理證書助你開啟高薪項目管理職場之路
- 7pmp證書助你馳騁職場與信息系統(tǒng)項目管理高薪秘籍曝光
- 8pmp證書助你開啟國際項目管理大門和信息系統(tǒng)項目管理師引領(lǐng)國內(nèi)項目管理之路
- 9PMP證書加持系統(tǒng)集成項目管理,開啟職場晉升新捷徑