成都公司:成都市成華區(qū)建設(shè)南路160號1層9號
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務(wù)大廈18樓
當(dāng)前位置:工程項目OA系統(tǒng) > 建筑OA系統(tǒng) > 軟件項目管理工具
2010年P(guān)MP美國項目管理考試習(xí)題及答案三十七
QUEST The basic terminology for networks includes:
A Activities, events, manpower, skill levels and slack.
B Activities, documentation, events, manpower and skill levels.
C Slack, activities, events, and time estimates.
D Time estimates, slack, sponsorship involvement, and activities.
E Time estimates, slack time, report writing, life cycle phases, and crashing times.
參考答案:C
QUEST The utility of network-based schedules:
A Reveals interdependencies.
B Facilitates "what if" exercises.
C Highlights critical activities.
D Provides information on resource requirements, time requirements and tradeoffs.
E All of the above.
參考答案:E
QUEST The major disadvantage of a bar chart is:
A Lack of time-phasing.
B Cannot be related to calendar dates.
C does not show activity interrelationships.
D Cannot be related to manpower planning.
E Cannot be related to cost estimates.
參考答案:C
QUEST The most common types of schedules are Gantt charts, milestone charts, line of balance, and:
A Networks.
B Time phased events.
C Calendar integrated activities.
D A and C only.
E B and C only.
參考答案:A

QUEST Scheduling is the process by which decisions are made concerning:
A Tasks to be accomplished.
B Personnel/organization that will be assigned to accomplish the task.
C Time when the tasks are to be completed.
D All of the above.
E A and C only.
參考答案:E
相關(guān)試題:
2010年P(guān)MP美國項目管理考試習(xí)題及答案三十六
試題推薦:
2010年P(guān)MP美國項目管理認(rèn)定考試全真模擬試題精選1
2010年P(guān)MP美國項目管理認(rèn)定考試全真模擬試題精選2
2010年P(guān)MP美國項目管理認(rèn)定考試全真模擬試題精選3
本文內(nèi)容來自自互聯(lián)網(wǎng)公開信息或用戶自發(fā)貢獻(xiàn),該文觀點僅代表作者本人,版權(quán)歸原作者所有。本站僅提供信息存儲空間服務(wù),不擁有所有權(quán),不承擔(dān)相關(guān)法律責(zé)任。若發(fā)現(xiàn)侵權(quán)或違規(guī)內(nèi)容請聯(lián)系電話4008352114或郵箱442699841@qq.com,核實后本網(wǎng)站將在24小時內(nèi)刪除侵權(quán)內(nèi)容。

