2010年P(guān)MP美國項目管理考試習(xí)題及答案四十一
QUEST Cost forecasting calculations include:
A EAC = ACWP + (BAC - BCWP)
B EAC = BAC/CPI
C EAC = ACWP + (BAC/CPI)
D All of the above.
E A and B
參考答案:E
QUEST The Cost Performance Index (CPI) measures
A total costs
B performance over a period of time
C costs at a point of time
D variable costs
E All of the above.
參考答案:C
QUEST Parametric cost estimating involves
A using the WBS to do bottom up estimates
B defining the perimeters of the life-cycle
C calculating the individual estimates of work packages
D using a statistical model to estimate costs
E A and C
參考答案:D
QUEST Which of the statements regarding benefit-cost analysis in the Special window are true?
A 1 and 2
B 2 and 3
C 1 and 3
D 1, 2 and 3
E None of the above.
參考答案:C

QUEST Present value measures
A the value to us today of future cash flows.
B the rate of return on an investment when we take account of cash inflows and outflows
C the current estimates of our project budget
D the dollars worth of work accomplished as of today
E All of the above.
參考答案:A
相關(guān)試題:
2010年P(guān)MP美國項目管理考試習(xí)題及答案四十
試題推薦:
2010年P(guān)MP美國項目管理認定考試全真模擬試題精選1
2010年P(guān)MP美國項目管理認定考試全真模擬試題精選2
2010年P(guān)MP美國項目管理認定考試全真模擬試題精選3
本文內(nèi)容來自自互聯(lián)網(wǎng)公開信息或用戶自發(fā)貢獻,該文觀點僅代表作者本人,版權(quán)歸原作者所有。本站僅提供信息存儲空間服務(wù),不擁有所有權(quán),不承擔(dān)相關(guān)法律責(zé)任。若發(fā)現(xiàn)侵權(quán)或違規(guī)內(nèi)容請聯(lián)系電話4008352114或郵箱442699841@qq.com,核實后本網(wǎng)站將在24小時內(nèi)刪除侵權(quán)內(nèi)容。