2010年P(guān)MP美國項目管理考試習(xí)題及答案五十
QUEST The salvage value of an asset is:
A The value of the scrap metal if a new asset were taken to a scrap yard.
B The value that an asset has on the books after one year of depreciation.
C The costs that have been sunk into the project to date.
D The expected cash value at the end of an assets useful life.
E A and D only.
參考答案:D
QUEST The budgeted cost of the work performed (BCWP) for a task that has just been completed can be calculated by:
A Multiplying the actual hours worked on the project by the budgeted labor rate.
B Multiplying the budgeted hours to complete the task by the budgeted labor rate.
C Dividing the actual hours required to complete the task by the budgeted labor rate.
D Cannot be determined.
E None of the above
參考答案:B
QUEST The methods and techniques for determining the economic costs, the environmental impact, the economic returns, and the probability for success are called:
A Feasibility studies.
B Bills of materials.
C Pert charts.
D Managerial reserves.
E None of the above
參考答案:A
QUEST The planned cost for the total project at its inception is called the _____.
A Cost of goods sold.
B Depreciable value.
C Budgeted cost.
D All of the above.
E B and C only.
參考答案:C

QUEST Which of the following is not a measure of the profitability of a project or program?
A Return on original investment.
B Net present value.
C Depreciation.
D Discounted cash flow.
E None of the above
參考答案:C
相關(guān)試題:
2010年P(guān)MP美國項目管理考試習(xí)題及答案四十九
試題推薦:
2010年P(guān)MP美國項目管理認(rèn)定考試全真模擬試題精選1
2010年P(guān)MP美國項目管理認(rèn)定考試全真模擬試題精選2
2010年P(guān)MP美國項目管理認(rèn)定考試全真模擬試題精選3
本文內(nèi)容來自自互聯(lián)網(wǎng)公開信息或用戶自發(fā)貢獻(xiàn),該文觀點僅代表作者本人,版權(quán)歸原作者所有。本站僅提供信息存儲空間服務(wù),不擁有所有權(quán),不承擔(dān)相關(guān)法律責(zé)任。若發(fā)現(xiàn)侵權(quán)或違規(guī)內(nèi)容請聯(lián)系電話4008352114或郵箱442699841@qq.com,核實后本網(wǎng)站將在24小時內(nèi)刪除侵權(quán)內(nèi)容。