2010年P(guān)MP美國項目管理考試習題及答案四十六
QUEST Which of the following is referred to as payback period:
A the number of periods required to recover the initial investment
B the rate of return on the investment
C the number of periods required to bring project cost back to the original budget, based on current performance
D loan payment schedule
E None of the above
參考答案:A
QUEST Which of the following is referred to as sunk cost:
A management reserve
B contingency fund
C cost budgeted for construction under water
D expended funds over which there is no further control
E forecasted budget over-runs
參考答案:D
QUEST The future value of an annual income flow of $1000 for 2 years at 10% is:
A ¥2,200
B ¥2,280
C ¥2,300
D ¥2,310
E None of the above
參考答案:D
QUEST The net present value of $110 one year from now at 10% is:
A ¥100
B ¥120
C ¥121
D $100 less taxes
E $100 less taxes and interest
參考答案:A

QUEST Which of the following depreciation methods provides for accelerated depreciation of an asset:
A Double declining balance.
B Straight line.
C Exponential depreciation
D Double sum of the years digits
E Double increasing balance
參考答案:A
相關(guān)試題:
2010年P(guān)MP美國項目管理考試習題及答案四十五
試題推薦:
2010年P(guān)MP美國項目管理認定考試全真模擬試題精選1
2010年P(guān)MP美國項目管理認定考試全真模擬試題精選2
2010年P(guān)MP美國項目管理認定考試全真模擬試題精選3
本文內(nèi)容來自自互聯(lián)網(wǎng)公開信息或用戶自發(fā)貢獻,該文觀點僅代表作者本人,版權(quán)歸原作者所有。本站僅提供信息存儲空間服務(wù),不擁有所有權(quán),不承擔相關(guān)法律責任。若發(fā)現(xiàn)侵權(quán)或違規(guī)內(nèi)容請聯(lián)系電話4008352114或郵箱442699841@qq.com,核實后本網(wǎng)站將在24小時內(nèi)刪除侵權(quán)內(nèi)容。