成都公司:成都市成華區(qū)建設(shè)南路160號1層9號
重慶公司:重慶市江北區(qū)紅旗河溝華創(chuàng)商務(wù)大廈18樓
當前位置:工程項目OA系統(tǒng) > 建筑OA系統(tǒng) > 軟件項目管理工具
2010年P(guān)MP美國項目管理考試習題及答案五十五
QUEST A _____ estimate prepared from layouts, sketches and flowsheets, should be accurate within (-10, +25%).
A Parametric
B Definitive.
C Budget
D Bottom up.
E Top down.
參考答案:C
QUEST The most precise or accurate estimate for determining project costs is the _____ estimate.
A Definitive.
B Analogy
C Budget
D Modified standards.
E Rule of thumb.
參考答案:A
QUEST Statistical cost estimating techniques (based upon history), are called _____ estimates and are a _____ approach.
A Definitive, bottom up.
B Analogy, top down.
C Parametric, bottom up.
D Parametric, top down.
E Analogy, bottom up.
參考答案:D
QUEST A(n) _____ system is designed to ensure the timely availability of nonhuman resources, and includes the cost in procurement, shipping/freight, storage and loss.
A Inventory control.
B Materials management.
C Procurement.
D All of the above.
E A and C only.
參考答案:B

QUEST There are two major types of reserves used on projects. The _____ is for (usually major) scope changes that were not considered as part of the original plan, whereas the _____ is to compensate for minor changes in estimating, escalation factors.
A Management reserve, unplanned allowance fund.
B Management reserve, contingency.
C Contingency fund, management reserve.
D Unplanned allowance fund, budgetary reserve.
E Unplanned reserve, planned reserve.
參考答案:C
相關(guān)試題:
2010年P(guān)MP美國項目管理考試習題及答案五十四
試題推薦:
2010年P(guān)MP美國項目管理認定考試全真模擬試題精選1
2010年P(guān)MP美國項目管理認定考試全真模擬試題精選2
2010年P(guān)MP美國項目管理認定考試全真模擬試題精選3
本文內(nèi)容來自自互聯(lián)網(wǎng)公開信息或用戶自發(fā)貢獻,該文觀點僅代表作者本人,版權(quán)歸原作者所有。本站僅提供信息存儲空間服務(wù),不擁有所有權(quán),不承擔相關(guān)法律責任。若發(fā)現(xiàn)侵權(quán)或違規(guī)內(nèi)容請聯(lián)系電話4008352114或郵箱442699841@qq.com,核實后本網(wǎng)站將在24小時內(nèi)刪除侵權(quán)內(nèi)容。

