2010年P(guān)MP美國項目管理考試習(xí)題及答案五十四
QUEST It is argumentative whether project managers actually control costs. Which of the following is the most common element over which the project manager may have some degree of control?
A Direct labor dollars
B Direct labor hours.
C Overhead rates.
D Procurement costs.
E None of the above.
參考答案:B
QUEST Company expenses such as auditing costs, supervision, office supplies, building rent and maintenance are elements of the:
A Capital budgeting process.
B Overhead rates.
C Contracts and administration costing system.
D Fringe benefits packages.
E None of the above.
參考答案:B
QUEST Management reserves are normally defined as a % of the total budget. As a project progresses, the project manager wants the $ value of management reserve to _____, whereas the customer wants the management reserve to _____.
A Increase, increase.
B Increase, decrease.
C Decrease, decrease.
D Decrease, increase.
E Remain the same, return to customer.
參考答案:E
QUEST The most effective means of determining the cost of a project is to price out the _____.
A Work breakdown structure.
B Linear responsibility chart.
C Project charter.
D Scope statement.
E Management plan.
參考答案:A

QUEST The most expensive phase of life cycle costing is:
A R & D.
B Applied research.
C Production
D Operations and support.
E Termination.
參考答案:D
相關(guān)試題:
2010年P(guān)MP美國項目管理考試習(xí)題及答案五十三
試題推薦:
2010年P(guān)MP美國項目管理認(rèn)定考試全真模擬試題精選1
2010年P(guān)MP美國項目管理認(rèn)定考試全真模擬試題精選2
2010年P(guān)MP美國項目管理認(rèn)定考試全真模擬試題精選3
本文內(nèi)容來自自互聯(lián)網(wǎng)公開信息或用戶自發(fā)貢獻,該文觀點僅代表作者本人,版權(quán)歸原作者所有。本站僅提供信息存儲空間服務(wù),不擁有所有權(quán),不承擔(dān)相關(guān)法律責(zé)任。若發(fā)現(xiàn)侵權(quán)或違規(guī)內(nèi)容請聯(lián)系電話4008352114或郵箱442699841@qq.com,核實后本網(wǎng)站將在24小時內(nèi)刪除侵權(quán)內(nèi)容。