2010年P(guān)MP美國項目管理考試習題及答案八十一
QUEST The core function of the project manager is
A Systems design
B Client interfacing
C Quality assurance
D integration
E參考答案:
參考答案:D
QUEST Situations calling for a matrix organization include outside pressure for dual focus, _____ and pressure for high information processing capability.
A Pressure for clear accountability
B Pressure for reduced duplication of effort
C Pressure for shared resources
D Pressure for formalized communication
E參考答案:
參考答案:C
QUEST Advantages of the functional (hierarchical) form of organization include _____ and creation of technical competence.
A Ease of horizontal coordination
B Clearly defined authority
C High information processing capability
D Single voice to customers
E參考答案:
參考答案:B
QUEST History has shown that project managers can be trained in a combination of ways. Which method is usually preferred by most companies?
A Experiential learning, on-the-job
B Formal education and special course (degreed programs)
C Professional activities, seminars
D Individual readings
E None of the above
參考答案:A

QUEST Which of the following organizational forms would be likely to have an individual with the title of Vice President for Project Management?
A Classical / traditional
B Pure project
C Matrix
D Project coordinator
E None of the above
參考答案:C
相關(guān)試題:
2010年P(guān)MP美國項目管理考試習題及答案八十