PMP認證考試練習題及參考答案(一)
1. communications is best described as:
a. an exchange of information.
b. providing written or oral directions.
c. consists of senders and receivers
d. effective listening.
e. all of the above考試大論壇
ans: e
2. fixed price contracts place more risk on the:
a. owner
b. buyer
c. seller
d. contractor
e. c or d
ans: e考試大(www.Examda。com)
3. life cycle costing is the total cost to the customer for the acquisition and ownership over its full life. life cycle costing categories include the cost
of _____, _____, and _____.
a. r & d, maintainability, operation and support.
b. r & d, production, operation and support.來源:考試大
c. acquisition, operations, maintenance.
d. production, operations, maintenance.
e. none of the above
ans: b
4. management by objectives assumes that the team:
a. is receptive to an unstructured environment.
b. does not require close supervision.
c. possesses a self directed philosophy
d. identifies with project objectives.來源:考試大
e. all of the above.
ans: e

5. quality may be defined as:
a. conformance to requirements.
b. fitness for use.
c. continuous improvement of products and services
d. appeal to the customer
e. all of the above except b來源:考試大
ans: e
6. since risk is associated with most projects, the best course of action is to:
a. cover all project risks by buying appropriate insurance
b. ignore the risks, since nothing can be done about them and move forward with the project in an expeditious manner.
c. avoid projects with clear and present risks
d. eliminate all known risks prior to the execution phase of the project
e. identify various risks and implement actions to mitigate their potential impact
ans: e
7. the process of choosing/documenting the best approach to achieve the project objectives is part of:
a. the scope baseline.
b. scope authorization來源:考試大網(wǎng)
c. scope definition
d. scope planning.
e. all of the above.
ans: d
8. time management is the allocation of time in a project's life cycle through the process of:
a. planning
b. estimating.
c. scheduling.
d. controlling
e. all of the above.
ans: e
9. a comprehensive definition of scope management would be:
a. managing a project in terms of its objective through the concept, development, implementation, and termination phases of a project.
b. approval of the scope baseline.http://ks.examda.com
c. approval of the detailed project charter.
d. configuration control.
e. approved detailed planning including budgets, resource allocation, linear responsibility charts and management sponsorship.
ans: a
10. cost plus percentage of cost contracts are more desirable for the:
a. owner
b. buyer
c. seller
d. contractor
e. c or d
ans: e
11. management styles associated with production environments, such as assembly lines commonly include:
a. a directing style of leadership.
b. a lack of confidence in their workerswww.Examda.CoM
c. assumption that workers lack ambition and dislike responsibility
d. a theory x style of leadership
e. all of the above.
ans: e
12. quality management:
a. is another name for careful inspections.
b. is inversely related to productivity.
c. is primarily the responsiblity of management.
d. is primarily the responsibility of the workers.
e. is essentially a motivational technique.
ans: c
本文內(nèi)容來自自互聯(lián)網(wǎng)公開信息或用戶自發(fā)貢獻,該文觀點僅代表作者本人,版權歸原作者所有。本站僅提供信息存儲空間服務,不擁有所有權,不承擔相關法律責任。若發(fā)現(xiàn)侵權或違規(guī)內(nèi)容請聯(lián)系電話4008352114或郵箱442699841@qq.com,核實后本網(wǎng)站將在24小時內(nèi)刪除侵權內(nèi)容。
本站推薦
- 1信息系統(tǒng)項目管理證書與PMP,為職業(yè)發(fā)展帶來的驚人機遇!
- 2信息系統(tǒng)項目管理師證書和pmp哪個更適合升職加薪?
- 3PMP項目管理泡軟件面臨的常見問題與挑戰(zhàn)分析
- 4PMP考試通過率及考生滿意度提升至90%以上:量化軟件項目管理成果的研究與實現(xiàn)
- 5歡迎登陸PMP項目管理系統(tǒng)——提升項目成功率的專業(yè)平臺!
- 6pmp證書和系統(tǒng)項目管理證書助你開啟高薪項目管理職場之路
- 7pmp證書助你馳騁職場與信息系統(tǒng)項目管理高薪秘籍曝光
- 8pmp證書助你開啟國際項目管理大門和信息系統(tǒng)項目管理師引領國內(nèi)項目管理之路
- 9PMP證書加持系統(tǒng)集成項目管理,開啟職場晉升新捷徑