PMP認證考試練習題及參考答案(二)
來源:考試大網(wǎng)1. the highest degrees of project risk and uncertainty are associated with the following phase of the project:
a. conceptual
b. execution
c. cut-over來源:www.examda.com
d. post project evaluation
e. a and d only
ans: a
2. the most common types of schedules are gantt charts, milestone charts, line of balance, and:
a. networks.
b. time phased events.
c. calendar integrated activities.
d. a and c only.
e. b and c only.
ans: a
3. which of the following is often overlooked in achieving effective communication?
a. speaking clearly
b. listening
c. interpreting
d. maintaining eye contact
e. manipulating the conversation
ans: b
4. which type of contract requires that the buyer keep the tightest labor/material cost control?
a. cost plus incentive fee
b. cost plus percentage of costs
c. cost plus fixed fee考試大論壇
d. firm fixed price
e. firm fixed price plus incentive
ans: b

5. a task-oriented family tree of activities is a:
a. detailed plan.
b. linear responsibility chart.
c. work breakdown structure.
d. cost account coding system.
e. work package description.
ans: c
6. adding 5 people to a 4 person team increases the communication channels by a factor of:
a. 2 times
b. 3 times
c. 4 times來源:考試大
d. 5 times
e. 6 times
ans: e
7. cost management includes:
a. cost estimating/forecasting.
b. cost budgeting/cost control.
c. cost applications.
d. all of the above.
e. a and b only.
ans: d
8. participative management:
a. involves the solicitation of information from all team members.
b. assumes that members avoid work and responsibility.
c. suggests the sharing of power and decision making.
d. employs a theory x style of leadership.
e. a and c
ans: e
9. the auditing function that provides feedback about the quality of output is referred to as:
a. quality control.
b. quality planning.
c. quality assurance.
d. quality improvement
e. all of the above.
ans: c
10. the lowest dollar amount 'at stake' is associated with the following phase of the project:
a. conceptual
b. execution來源:www.examda.com
c. cut-over
d. post project evaluation
e. a and d only
ans: a
11. the major disadvantage of a bar chart is:
a. lack of time-phasing.
b. cannot be related to calendar dates.
c. does not show activity interrelationships.
d. cannot be related to manpower planning.
e. cannot be related to cost estimates.
ans: c
12. which contract type consists of - target costs & profit, ceiling prices and shared ratio of risk?
a. cost plus incentive fee
b. cost plus percentage of costs
c. cost plus fixed fee
d. firm fixed pricewww.Examda.CoM
e. firm fixed price plus incentive
ans: e
本文內(nèi)容來自自互聯(lián)網(wǎng)公開信息或用戶自發(fā)貢獻,該文觀點僅代表作者本人,版權(quán)歸原作者所有。本站僅提供信息存儲空間服務,不擁有所有權(quán),不承擔相關(guān)法律責任。若發(fā)現(xiàn)侵權(quán)或違規(guī)內(nèi)容請聯(lián)系電話4008352114或郵箱442699841@qq.com,核實后本網(wǎng)站將在24小時內(nèi)刪除侵權(quán)內(nèi)容。
本站推薦
- 1信息系統(tǒng)項目管理證書與PMP,為職業(yè)發(fā)展帶來的驚人機遇!
- 2信息系統(tǒng)項目管理師證書和pmp哪個更適合升職加薪?
- 3PMP項目管理泡軟件面臨的常見問題與挑戰(zhàn)分析
- 4PMP考試通過率及考生滿意度提升至90%以上:量化軟件項目管理成果的研究與實現(xiàn)
- 5歡迎登陸PMP項目管理系統(tǒng)——提升項目成功率的專業(yè)平臺!
- 6pmp證書和系統(tǒng)項目管理證書助你開啟高薪項目管理職場之路
- 7pmp證書助你馳騁職場與信息系統(tǒng)項目管理高薪秘籍曝光
- 8pmp證書助你開啟國際項目管理大門和信息系統(tǒng)項目管理師引領國內(nèi)項目管理之路
- 9PMP證書加持系統(tǒng)集成項目管理,開啟職場晉升新捷徑