PMP認(rèn)證考試練習(xí)題及參考答案(五十六)
申請(qǐng)免費(fèi)試用、咨詢電話:400-8352-114
1 In which of the following contract types is it easier to change the scope of the contract:A firm fixed price
B fixed price plus incentive fee
C cost plus percentage of cost
D letter contract
E None of the above.
ans:C
2 Which of the following processes allow an unsuccessful bidder to seek remedy for contract award to another bidder.
A bid protest
B bid review
C award Protest
D award review
E any of the above processes can be used
ans:A
3 The "buy or make" decision is usually made during the:
A acquisition cycle
B contract evaluation cycle
C requirements cycle
D pre-award cycle
E at any time that is convenient for the project manager
ans:C
4 Back charges refers to:
A transferring charges from sub-contractors to the owner
B adjusting payments to reflect late invoices consequence
C the cost of corrective action taken by the owner and charged to the contractor for non-conformance
D gaining restitution from the owner for non payment
E C and D only
ans:C
5 Which of the following is equivalent to a lump sum contract:
A fixed price contract
B price fixing contract
C purchase order
D All of the above.
E B and C only
ans:A
6 Which of the following terms is used to describe the receipt issued by a carrier for items to be delivered to a third party:
A free on board
B receipt for merchandise
C packaging list
D loading list
E bill of lading
ans:E
7 Which of the following is associated with a buyer's request for material to meet a particular need:
A material warranty
B material guarantees
C implied warranty of salability
D implied warranty of fitness for a particular purpose
E A and C only
ans:D
8 The comprehensive review of a contractor's technical performance, cost performance, and delivery schedule, is referred to as:
A post project evaluation
B post contract evaluation
C post mortem
D procurement performance evaluation
E contractor's performance evaluation
ans:E
9 Which of the following terms refers to the situation where the work is being used for the purpose intended and so certified:
A beneficial completion
B substantial completion
C project completion
D contract closeout
E final completion
ans:B
10 A deficiency in characteristics that render the quality of the material/service unacceptable is usually referred to as:
A defective
B defect
C non-conformance
D poor workmanship
E lack of fitness for use
ans:C
11 The formal invitation to submit a price for specified goods/services is usually referred to as:
A request for proposal
B request for quotation
C tender invitation
D bid invitation
E A and B only
ans:B
12 Which of the following is not part of contract administration
A contract award
B performance control
C financial control
D contract closeout
E All of the above are parts of contract administration.
ans:A
本文內(nèi)容來(lái)自自互聯(lián)網(wǎng)公開(kāi)信息或用戶自發(fā)貢獻(xiàn),該文觀點(diǎn)僅代表作者本人,版權(quán)歸原作者所有。本站僅提供信息存儲(chǔ)空間服務(wù),不擁有所有權(quán),不承擔(dān)相關(guān)法律責(zé)任。若發(fā)現(xiàn)侵權(quán)或違規(guī)內(nèi)容請(qǐng)聯(lián)系電話4008352114或郵箱442699841@qq.com,核實(shí)后本網(wǎng)站將在24小時(shí)內(nèi)刪除侵權(quán)內(nèi)容。
本站推薦
- 1信息系統(tǒng)項(xiàng)目管理證書(shū)與PMP,為職業(yè)發(fā)展帶來(lái)的驚人機(jī)遇!
- 2信息系統(tǒng)項(xiàng)目管理師證書(shū)和pmp哪個(gè)更適合升職加薪?
- 3PMP項(xiàng)目管理泡軟件面臨的常見(jiàn)問(wèn)題與挑戰(zhàn)分析
- 4PMP考試通過(guò)率及考生滿意度提升至90%以上:量化軟件項(xiàng)目管理成果的研究與實(shí)現(xiàn)
- 5歡迎登陸PMP項(xiàng)目管理系統(tǒng)——提升項(xiàng)目成功率的專(zhuān)業(yè)平臺(tái)!
- 6pmp證書(shū)和系統(tǒng)項(xiàng)目管理證書(shū)助你開(kāi)啟高薪項(xiàng)目管理職場(chǎng)之路
- 7pmp證書(shū)助你馳騁職場(chǎng)與信息系統(tǒng)項(xiàng)目管理高薪秘籍曝光
- 8pmp證書(shū)助你開(kāi)啟國(guó)際項(xiàng)目管理大門(mén)和信息系統(tǒng)項(xiàng)目管理師引領(lǐng)國(guó)內(nèi)項(xiàng)目管理之路
- 9PMP證書(shū)加持系統(tǒng)集成項(xiàng)目管理,開(kāi)啟職場(chǎng)晉升新捷徑