2010年P(guān)MP美國項目管理考試習(xí)題及答案七十五
QUEST Which of the following is based on an individual identification with a more powerful person.
A expert power
B reward power
C referent power
D A and B.
E A and C
參考答案:C
QUEST Which of the following results are Win/Win conflict resolution?
A compromising
B forcing
C problem solving
D smoothly
E withdraw
參考答案:C
QUEST Which of the following organizations has the best technical project control?
A matrix
B functional
C projectized
D B and C
E A and B
參考答案:D
QUEST The functional organization is effective with a mature product or single product line.
A TRUE
B FALSE
C參考答案:
D參考答案:
E參考答案:
參考答案:A

QUEST The strong matrix versus a weak matrix.
A team members are more likely to be assigned to the project office in a strong matrix
B strong matrix is more difficult to manage.
C the balance of power has shifted away from the PM.
D functional managers no longer has control over the technical processes.
E All of the above.
參考答案:A
相關(guān)試題:
2010年P(guān)MP美國項目管理考試習(xí)題及答案七十四
試題推薦:
2010年P(guān)MP美國項目管理認定考試全真模擬試題精選1
2010年P(guān)MP美國項目管理認定考試全真模擬試題精選2
2010年P(guān)MP美國項目管理認定考試全真模擬試題精選3
本文內(nèi)容來自自互聯(lián)網(wǎng)公開信息或用戶自發(fā)貢獻,該文觀點僅代表作者本人,版權(quán)歸原作者所有。本站僅提供信息存儲空間服務(wù),不擁有所有權(quán),不承擔相關(guān)法律責任。若發(fā)現(xiàn)侵權(quán)或違規(guī)內(nèi)容請聯(lián)系電話4008352114或郵箱442699841@qq.com,核實后本網(wǎng)站將在24小時內(nèi)刪除侵權(quán)內(nèi)容。