PMP認(rèn)證考試練習(xí)題及參考答案(五十三)

申請(qǐng)免費(fèi)試用、咨詢(xún)電話(huà):400-8352-114

1 Monte Carlo simulation:
A Was originally developed by Dr. Carlo
B Is a European technique for assessing project risks
C assumes the future risk events will occur at random according to predetermined probability distributions
D is a technique to stimulate create risk event resolution
E A, B and C only
ans:C
2 Which of the following actions is an example of risk response:
A adjust project parameters (scope, time, quality ...)
B reduce the probability of potential project risk events
C reduce the consequences of potential project risk events
D wait until a problem actually happens, then deal with it in the most effective and efficient manner.
E A, B and C only
ans:E
3 Total project risk can be defined as:
A the sum of the probabilities of project risks events times the sum of consequences of those risks
B the sum of the products of each project risk event times its consequences
C the sum of the consequences of all project risk events
D the sum of the probabilities of all project risk events
E 1 - the sum of the probabilities of all project risk events. 來(lái)源:考
ans:B
4 The utility of a risk seeker is:
A negatively exponential
B positively skewed
C increasing
D decreasing
E symmetrical
ans:C
5 Giving a part of project work to a contractor is an example of:
A risk mitigation
B risk assignment
C risk delegation
D risk deflection
E risk assumption
ans:D
6 Risk management methodology should be adhered to in:
A construction projects
B system projects
C complex projects
D large projects
E All of the above.
ans:E
7 Which of the following activities can be considered as part of risk mitigation
A risk identification
B purchasing insurance
C assessment of outcomes
D assessment of probabilities
E C and D only
ans:B
8 Which of the following scheduling methods uses more of the risk management concepts:
A ADM
B PDM
C CPM
D PERT
E Gantt
ans:D
9 Which of the following utility functions reflects risk-aversion:
A uniform
B increasing
C decreasing
D exponential
E B and D only
ans:C
10 To calculate the expected value of an outcome:
A divide the value of each outcome by its probability, then add the results.
B divide the value of the desired outcome by the value all possible outcomes
C multiply the value of each outcome by its probability, then add the results
D use linear regression to assess the expected value of the outcome
E B and D only 來(lái)源:考
ans:C
11 Which of the following is most closely associated with pure risk:
A profit and loss
B personnel turnover
C insurance
D market fluctuations
E A and D only
ans:C
12 Which of the following is most closely associated with business risk:
A profit and loss
B personnel turnover
C workmen's compensation
D liability insurance
E All of the above.
ans:A
網(wǎng)站提醒和聲明

本文內(nèi)容來(lái)自自互聯(lián)網(wǎng)公開(kāi)信息或用戶(hù)自發(fā)貢獻(xiàn),該文觀點(diǎn)僅代表作者本人,版權(quán)歸原作者所有。本站僅提供信息存儲(chǔ)空間服務(wù),不擁有所有權(quán),不承擔(dān)相關(guān)法律責(zé)任。若發(fā)現(xiàn)侵權(quán)或違規(guī)內(nèi)容請(qǐng)聯(lián)系電話(huà)4008352114或郵箱442699841@qq.com,核實(shí)后本網(wǎng)站將在24小時(shí)內(nèi)刪除侵權(quán)內(nèi)容。

發(fā)布:2026-02-28 10:14    編輯:xiaona    [打印此頁(yè)]    [關(guān)閉]

泛普軟件項(xiàng)目管理工具其他應(yīng)用

項(xiàng)目管理工具 禪道項(xiàng)目管理軟件 夢(mèng)龍項(xiàng)目管理軟件 微軟項(xiàng)目管理軟件 裝飾管理系統(tǒng) 裝修預(yù)算軟件 項(xiàng)目計(jì)劃軟件 項(xiàng)目進(jìn)度管理軟件 軟件項(xiàng)目管理工具 材料管理軟件 工程項(xiàng)目管理軟件系統(tǒng) 項(xiàng)目管理系統(tǒng) 施工管理軟件 建筑工程項(xiàng)目管理軟件 工程管理軟件