PMP認證考試練習題(十八)(中英文)

申請免費試用、咨詢電話:400-8352-114

1. If a risk event has a chance of occurring 15 times out of 45 times, based on experiences with like events, what is the probability that the event will occur on the next project?
90%
45%
15%
33%

如果一個風險事件的發(fā)生機會是45次中出現15次, 基于類似事件的經驗, 在下個項目上,這個風險事件發(fā)生的概率是多少?
a. 90%
b. 45%
c. 15%
d. 33%

2. During which phase of a project is the level of uncertainty the greatest?
Design
Development/Execution
Conceptual
Phase-out

在項目的哪一階段, 不確定性程度最大?
a. 設計
b. 開發(fā)/實行
c. 構思立項
d. 結束

3. The expected value of a risk event is calculated by multiplying the .
Likelihood of the event by the consequence of its occurrence
Likelihood of the event by the number of risk events
The number of risk events by the consequences of their occurrence
The likelihood of the greatest risk event by the consequence of the smallest risk event

計算風險事件的期望值是通過乘上什么
a. 事件發(fā)生的可能性乘以事件發(fā)生的結果
b. 事件發(fā)生的可能性乘以風險事件發(fā)生次數
c. 風險事件發(fā)生次數乘以事件發(fā)生的結果
d. 最大風險的事件發(fā)生可能性乘以最小風險的事件的發(fā)生的結果

4. Which of the following is not an external, unpredictable risk?
Changes in government regulations
Natural disasters
Vandalism
Inflation

下面哪一事項不是一個外部的不可預測的風險?
a. 政府管制的變化
b. 自然災禍
c. 有意的破壞
d. 通貨膨脹

5. The techniques and methods used to reduce or control risk are part of which of the following mechanisms:
Risk assessment
Risk response planning
Lessons learned
Risk analysis

用來減少或者控制風險的技術和方法是下列哪一機制的一部份:
a. 風險評估
b. 風險應變規(guī)劃
c. 經驗教訓學習
d. 風險分析

6. A project manager sends the electrical engineer an e-mail message asking her to prepare a detailed technical report per some instructions given in the e-mail. A week later, the electrical engineer’s department manager visits the project manager to complain that his engineer had spent 45 hours preparing the 80-page report. The project manager indicates that he thought the report would be only 4 pages long. The problem here is one of:
Lack of feedback
Too many instructions
Too much communication
Lack of trust

A 項目經理發(fā)送給電子工程師一個電子郵件信息, 要求她準備一份詳細的技術報告, 并在電子郵件中附注了某些說明. 一周后,電子工程師所在部門的經理拜訪項目經理以抱怨道: 該電子工程師已經花費了45 小時做出80頁的報告. 項目經理指出:他認為報告只需要有 4 頁長. 這里的問題是:
a. 缺乏反饋
b. 指令太多
c. 溝通太多
d. 缺乏信任

7. A line manager possesses information, which the project team needs, but withholds the information. This is a type of:
Confrontation
Information filtering
Region of influence
Communication power base

產品經理有項目團隊所需要的信息, 但是隱瞞住該信息. 這是一種:
a. 正面對抗
b. 信息過濾
c. 影響區(qū)域
d. 基本溝通力

網站提醒和聲明

本文內容來自自互聯網公開信息或用戶自發(fā)貢獻,該文觀點僅代表作者本人,版權歸原作者所有。本站僅提供信息存儲空間服務,不擁有所有權,不承擔相關法律責任。若發(fā)現侵權或違規(guī)內容請聯系電話4008352114或郵箱442699841@qq.com,核實后本網站將在24小時內刪除侵權內容。

發(fā)布:2026-02-28 10:05    編輯:xiaona    [打印此頁]    [關閉]

泛普軟件項目管理工具其他應用

項目管理工具 禪道項目管理軟件 夢龍項目管理軟件 微軟項目管理軟件 裝飾管理系統 裝修預算軟件 項目計劃軟件 項目進度管理軟件 軟件項目管理工具 材料管理軟件 工程項目管理軟件系統 項目管理系統 施工管理軟件 建筑工程項目管理軟件 工程管理軟件