30. As part of the contract close-out, project management should document the:a. statement of work.
b. payment schedules.
c. formal acceptance.
d. change control process.
31. The process of performance reporting includes all of the following except:
a. status reporting.
b. progress reporting.
c. forecasting.
d. product analysis.
32. Constructive team roles include:
a. investigator, clarifier, and closer.
b. compromiser, blocker, and closer.
c. initiator, encourager, and gatekeeper.
d. investigator, recognizer, and summarizer.
33. Which of the following statements concerning contract type is correct?
a. fixed price contracts offer buyers the highest potential risk.
b. cost reimbursable contracts offer buyers the lowest potential risk.
c. fixed price contracts are illegal in most regulated industries.
d. lump sum contracts offer sellers the highest potential risk.
34. A Work Breakdown Structure numbering system should allow project staff to:
a. identify the level at which individual WBS elements are found.
b. identify configuration management milestones.
c. estimate the costs of WBS elements.
d. provide project justification.
35. All of the following are true quality statements except:
a. Computer-aided design systems can improve quality, but only at the expense of an increase in the cost of design.
b. Project quality management must address both management of the project and the product of the project.
c. Recognition of key actions required of each team member is necessary to meet quality objectives.
d. Quality improvement depends upon better definition and increased awareness of the requirements/specifications.
36. A project was estimated to cost .5 million and scheduled to last six months. After three months, the earned value analysis shows the following: EV = 0,000, PV = 0,000, and AC = 0,000. The schedule and cost variances are:
a. SV = -0,000 / CV = -0,000.
b. SV = -,000 / CV = +0,000.
c. SV = +0,000 / CV = +0,000.
d. SV = +0,000 / CV = -0,000.
37. A precise summary of a physical item, procedure, or service for implementation of an item or service is called a:
a. work package.
b. baseline description.
c. product description.
d. work breakdown structure.
38. All of the following are examples of tools often used in cost estimating except:
a. parametric modeling.
b. duration estimating.
c. bottom-up estimating.
d. analogous estimating.
39. The most crucial time for project risk assessment is:
a. when a problem surfaces.
b. during the planning phase.
c. during the close-out phase.
d. after the schedule is published.
40. Inputs used during scope planning include all of the following except:
a. constraints.
b. project charter.
c. budget/cost analysis.
d. product description.
41. A scope statement is important because it:
a. provides the basis for making future project decisions.
b. provides an executive summary of the project for sponsors.
c. documents approval of the project for the stakeholders.
d. provided criteria for measuring total project cost.
本文內(nèi)容來(lái)自自互聯(lián)網(wǎng)公開(kāi)信息或用戶自發(fā)貢獻(xiàn),該文觀點(diǎn)僅代表作者本人,版權(quán)歸原作者所有。本站僅提供信息存儲(chǔ)空間服務(wù),不擁有所有權(quán),不承擔(dān)相關(guān)法律責(zé)任。若發(fā)現(xiàn)侵權(quán)或違規(guī)內(nèi)容請(qǐng)聯(lián)系電話4008352114或郵箱442699841@qq.com,核實(shí)后本網(wǎng)站將在24小時(shí)內(nèi)刪除侵權(quán)內(nèi)容。
本站推薦
- 1信息系統(tǒng)項(xiàng)目管理證書(shū)與PMP,為職業(yè)發(fā)展帶來(lái)的驚人機(jī)遇!
- 2信息系統(tǒng)項(xiàng)目管理師證書(shū)和pmp哪個(gè)更適合升職加薪?
- 3PMP項(xiàng)目管理泡軟件面臨的常見(jiàn)問(wèn)題與挑戰(zhàn)分析
- 4PMP考試通過(guò)率及考生滿意度提升至90%以上:量化軟件項(xiàng)目管理成果的研究與實(shí)現(xiàn)
- 5歡迎登陸PMP項(xiàng)目管理系統(tǒng)——提升項(xiàng)目成功率的專業(yè)平臺(tái)!
- 6pmp證書(shū)和系統(tǒng)項(xiàng)目管理證書(shū)助你開(kāi)啟高薪項(xiàng)目管理職場(chǎng)之路
- 7pmp證書(shū)助你馳騁職場(chǎng)與信息系統(tǒng)項(xiàng)目管理高薪秘籍曝光
- 8pmp證書(shū)助你開(kāi)啟國(guó)際項(xiàng)目管理大門(mén)和信息系統(tǒng)項(xiàng)目管理師引領(lǐng)國(guó)內(nèi)項(xiàng)目管理之路
- 9PMP證書(shū)加持系統(tǒng)集成項(xiàng)目管理,開(kāi)啟職場(chǎng)晉升新捷徑