2010年PMP美國項目管理考試習題及答案33
QUEST Which of the following is equivalent to a lump sum contract:
A fixed price contract
B price fixing contract
C purchase order
D All of the above.
E B and C only
參考答案:A
QUEST Which of the following terms is used to describe the receipt issued by a carrier for items to be delivered to a third party:
A free on board
B receipt for merchandise
C packaging list
D loading list
E bill of lading
參考答案:E
QUEST Which of the following is associated with a buyer's request for material to meet a particular need:
A material warranty
B material guarantees
C implied warranty of salability
D implied warranty of fitness for a particular purpose
E A and C only
參考答案:D
QUEST The comprehensive review of a contractor's technical performance, cost performance, and delivery schedule, is referred to as:
A post project evaluation
B post contract evaluation
C post mortem
D procurement performance evaluation
E contractor's performance evaluation
參考答案:E
![]()
QUEST Which of the following terms refers to the situation where the work is being used for the purpose intended and so certified:
A beneficial completion
B substantial completion
C project completion
D contract closeout
E final completion
參考答案:B
相關試題:
2010年PMP美國項目管理考試習題及答案32
試題推薦:
2010年PMP美國項目管理認定考試全真模擬試題精選1
2010年PMP美國項目管理認定考試全真模擬試題精選2
2010年PMP美國項目管理認定考試全真模擬試題精選3
本文內(nèi)容來自自互聯(lián)網(wǎng)公開信息或用戶自發(fā)貢獻,該文觀點僅代表作者本人,版權歸原作者所有。本站僅提供信息存儲空間服務,不擁有所有權,不承擔相關法律責任。若發(fā)現(xiàn)侵權或違規(guī)內(nèi)容請聯(lián)系電話4008352114或郵箱442699841@qq.com,核實后本網(wǎng)站將在24小時內(nèi)刪除侵權內(nèi)容。